Power Generation Support Infrastructure

The Scope: Design and Supply 6 x IP66 Enclosed Motor Control Centre / Power Distribution Panels for Generator Supply and Distribution Services.

This project involved 2 sets of identical panels for the generator supply infrastructure and reliability upgrade works in South Australia.

This was a variation on the standard type tested IP43 M Series design, and involved an additional IP66 outdoor enclosure facilitating full outdoor installation of the MCCs.

The overall installation included 4 x 2500 Amp MCCs and 2 x 960 Amp MCCs, with each MCC including Fault Current Limitation via line side fuses to achieve 100kA total apparatus fault withstand capability.

  • Type Co-ordination and Discrimination Design
  • Electrical Schematic and Termination Drawings
  • Sheetmetal Construction and Fabrication
  • Motor Control Centre Supply and Installation
  • IP66 Custom Outdoor Enclosure

The project was completed and assembled at the Client’s premises in South Australia, on-time and on-budget.

 

PROJECT NUMBER: 0252
END USER: South Australian Government
LOCATION: Edinburgh / Lonsdale
SERVICES CATEGORY: LV Products, Engineering
CONTRACT TYPE: Lump Sum
CONTRACT DETAILS: Design, Manufacture & Install
DURATION: Aug - Oct 2017